HAREHILLS COMMUNITY HEALTH CENTRE – HC2 – Update for Milan Street patients.
90% of the windows are already fitted. Plastering is 45% completed. 30% of the cladding panels on the outside have been fitted. The scaffolding has already started coming down as the build progresses. All the internal blockwork has been completed and the external brickwork is 90% complete too. We now have the Joiners and Decorators in to start work on the inside. The car park is ready for paving and tarmac and the concrete on the pedestrian ramp for access will start next week.
Milan Street patients: We will be sending you regular reminders to you to keep you updated about the move scheduled for December this year!